GUSSE 2025 PT Sinta Prima Feedmill CileungsiThursday, November 20, 2025GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC11771 :,- - Pengajuan code GSC117 Beton Readymix K300 : 240,00 m3 @ Rp995.000,00 = Rp238.800.000,00 :,- Minggu ini :,- Beton Readymix K300 :,- 117-7 ,- 7,00 m3 @ Rp995.000,00 = Rp6.965.000,00:,- Total sampai minggu ini :,- Beton Readymix K300 :,- 52,50 @ Rp995.000,00 = Rp52.237.500,00 110GSC1125
lanjut ke proses
Mohon permintaan pembeli beton Redy mix di proses dan di bayarkanTks
GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC1177 PROYEK GUSSE CILEUNGSI dan Bayar 25 Nopember 2025NO.BKK : 110GSC1125- GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC1177 : 7.731.000,00 (include ppn)- BS yang BELUM diselesaikan MAS ASYARI : 10.400.000,- segera diselesaikan- SISTEM ............. TUNTASEVALUASI UNTUK GUSSEIRESCHEDULE-1 S/D 30 NOPEMBER 2025- Progres RIEL 23-11-2025 :- a. WWTP-1 = 20,06%- b. WWTP-2 = 50,81%- Rencana Progres :- a. WWTP-1 = 2,66%- b. WWTP-2 = 42,76%- Deviasi : --- a. WWTP-1 =--20,08% (NEGATIF)- b. WWTP-2 =- 48,35% (NEGATIF)- PROFIT VOOR (rapat dan tetap) :8,5%- Profit Rekap Voor (bergerak) : 4,54%- Stock : 254.032.099,79- Profit Riel Progres setelah stock: ---11,65% (negatif) = ---Rp73.918.784,54 (negatif)- Belum TERMASUK Gaji Pelaksana - Harus ada penghematan dan efesiensi. Evaluasi Volume dan harga satuan terus menerus , AGAR bisa Profit diatas 12%- Maka GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC1177 PROYEK GUSSE CILEUNGSI dan Bayar 25 Nopember 2025 : Rp 6.700.000,00PEMBAYARAN : GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC1177 PROYEK GUSSE CILEUNGSI dan Bayar 25 Nopember 2025- Rek. ASYARI : Diinput SUPRIADI- Dibayarkan : Rp 6.700.000,00- NO.BKK : 110GSC1125 dan Data Disiapkan SUPRIADI
Data pembayaran sudah disiapkan
GUSSE 2025 PT Sinta Prima Feedmill Cileungsi
ReplyDeleteThursday, November 20, 2025
GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC1177
1
:,- - Pengajuan code GSC117 Beton Readymix K300 : 240,00 m3 @ Rp995.000,00 = Rp238.800.000,00
:,- Minggu ini
:,- Beton Readymix K300
:,- 117-7
,- 7,00 m3 @ Rp995.000,00 = Rp6.965.000,00
:,- Total sampai minggu ini
:,- Beton Readymix K300
:,- 52,50 @ Rp995.000,00 = Rp52.237.500,00
110GSC1125
lanjut ke proses
ReplyDeleteMohon permintaan pembeli beton Redy mix di proses dan di bayarkan
ReplyDeleteTks
GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC1177 PROYEK GUSSE CILEUNGSI dan Bayar 25 Nopember 2025
ReplyDeleteNO.BKK : 110GSC1125
- GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC1177 : 7.731.000,00 (include ppn)
- BS yang BELUM diselesaikan MAS ASYARI : 10.400.000,- segera diselesaikan
- SISTEM ............. TUNTAS
EVALUASI UNTUK GUSSEI
RESCHEDULE-1 S/D 30 NOPEMBER 2025
- Progres RIEL 23-11-2025 :
- a. WWTP-1 = 20,06%
- b. WWTP-2 = 50,81%
- Rencana Progres :
- a. WWTP-1 = 2,66%
- b. WWTP-2 = 42,76%
- Deviasi : --
- a. WWTP-1 =--20,08% (NEGATIF)
- b. WWTP-2 =- 48,35% (NEGATIF)
- PROFIT VOOR (rapat dan tetap) :8,5%
- Profit Rekap Voor (bergerak) : 4,54%
- Stock : 254.032.099,79
- Profit Riel Progres setelah stock: ---11,65% (negatif) = ---Rp73.918.784,54 (negatif)
- Belum TERMASUK Gaji Pelaksana
- Harus ada penghematan dan efesiensi. Evaluasi Volume dan harga satuan terus menerus , AGAR bisa Profit diatas 12%
- Maka GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC1177 PROYEK GUSSE CILEUNGSI dan Bayar 25 Nopember 2025 : Rp 6.700.000,00
PEMBAYARAN : GSC - PERMINTAAN BS PEMBELIAN BETON READYMIX K300 - GSC1177 PROYEK GUSSE CILEUNGSI dan Bayar 25 Nopember 2025
- Rek. ASYARI : Diinput SUPRIADI
- Dibayarkan : Rp 6.700.000,00
- NO.BKK : 110GSC1125 dan Data Disiapkan SUPRIADI
Data pembayaran sudah disiapkan
ReplyDelete